In Pursuit of the Perfect Plant: A Business and Technical Guide
Chapter 6, Strategy, Coordination, and Planning
Plant managers often have to make difficult production decisions quickly. In this excerpt, find out how to base supply chain management decisions on strategic models for success and learn what questions a manager should ask when faced with supply chain challenges.

In Pursuit of the Perfect Plant: A Business and Technical Guide, Ch. 6
Table of contents:
An intro to strategy, coordination and planning
Sales and operations planning for manufacturing
Manufacturing plant information management
Information integration in manufacturing: Process control and planning software
Manufacturing supply chain strategy: KPI and execution in process industries
Manufacturing operations management and planning based on strategic models

When the Rubber Hits the Road: Decision-Making Based on
Strategic Models
"Suppose you have to decide to shut down a line or defer maintenance
30 days," Moulton continued. "The less time it takes for corporate to make a
decision, the better off the person making the call in the plant will be. Often,
these are seat-of-the-pants, intuitive decisions. For instance, say a pump goes
down on New Year's Eve. The plant foreman calls a maintenance guy, who
looks at the spare pump's record. If it looks good, he makes an instant decision
not to call out a crew that he knows will cost triple time. If he can't make that
decision, it rolls up one level, and it keeps on rolling up until someone finds
the economics that will enable a good decision. Absent the data, the plant
manager will go to the floor and say, 'Damn it, you keep this place running,
whatever it costs.' He knows what his risk-reward is. He's going to get an 'Atta
boy' if he gets the thing fixed that night, regardless if it costs him $10,000 to
call out guys from the party. He also knows that if it stays broken, he's going
to get canned."
 |
|
| This excerpt from In Pursuit of the Perfect Plant: A Business and Technical Guide by Pat Kennedy, Vivek Bapat, Paul Kurchina is reprinted here with permission from Evolved Technologist Press, Copyright 2008. |
|
|
 |
 |
"But there's got to be an alternate approach, one that's a bit more sane,"
Bala said.
"The alternative is arming yourself with more facts and figures," Moulton
said. "The shift foreman needs to know, for instance, that every time he
loses capacity because of an ailing pump, it's going to cost $10.00 a barrel.
Therefore, he always needs to know the condition of his spare pump. If he's
not willing to risk that $10-a-barrel shutdown, he also needs to know it's only
going to cost $3,000 to call out the repair crew to make things right. In a more sophisticated plant, better data enables you to reach the same decision with greater confi dence. You know that your mean-time-between-failure for this
kind of pump is three years. This pump is only a year old, so there's no reason
to panic."
Best Questions
"Let's now take a look at our best questions," Moulton said. "Assuming you
have an hour to walk into a plant and fi re away at anyone, here's a list of
questions to ask to get a good sense of how well their strategy and planning
are coordinated with the realities of the plant. The answers provided by
managers and executives at a plant should indicate how well the strategy,
coordination, and planning are working together."
Moulton wrote on the board:
1.) Is this plant run as part of an overall supply chain?
"Do you make what you sell," Moulton said, "or do you sell what you
make? Are you the original manufacturer, like an auto-maker, or are you
reconstituting a commodity, with a market on either side of the plant? Refi ning
would be a good example of the latter. Generally, this would be a question to
ask senior management before you went down to the fl oor. It helps determine
whether you're looking at a discrete factory or a process factory."
2.) Are production planning and maintenance planning
done together?
3.) When you make scheduling decisions, do you know the
impact on the other guy's KPI?
4.) Do you implement any mechanism to systematically
and comprehensively address these issues
and make decisions?
5.) Does top management understand the risk or degree
of control of a planned or unplanned shutdown?
6.) If there is an unscheduled breakdown or shutdown, can
you opportunistically schedule other maintenance, or are
you just coping? To what degree are you able to look at
that as being 'in control' or 'out of control?'
7.) How reliable are your metrics for managing the plant?
"I have a question about number six," Mulcahy said. "What sort of answer
might suggest that you need to contend with certain risks in the way you run
the plant?"
"The worst answer is a blank stare," Moulton said. "The best answer would
be that they'd established an acceptable level of risk and know exactly what
the plant can tolerate—say, an 8% risk of breakdown. For example, they might
have spreadsheets and hard data and some concrete information on which they can base an estimate. That's defi nitely better than nothing. If they've been running a production environment and gathering data about how
long things will run for before they need to be shut down and repaired—
a.k.a. preventative maintenance—they'll be able to provide an estimate of
the failure-free interval and an assessment of a guaranteed failure point.
Somewhere between the guaranteed failure point and the failure-free interval
there's a curve that starts to change. As you cruise through the failure-free
interval, your risk starts to increase.
"In other words, if you had 24 hours between the failure-free interval and
the guaranteed failure point, then when you're at 12 hours over the failurefree
interval is your risk of a breakdown now at 50%? Maybe, maybe not. It
depends on the piece of equipment. But if you can assess the amount of risk in
that little interval, and then add up the risk over all the pieces of equipment,
you can get an assessment of the overall risk in the plant."
"OK, so the overall risk is the average risk of all the equipment in the whole
plant. That is easy," Bala said. "In sum: the more data you have, the better
decisions you can make."
"I have more best questions," Moulton said, returning to the board.
More Best Questions
8.) Does the plant compare its planning program prediction
with what's actually happening in the plant?
9.) Do you know what S&OP is?
"I want to tell you a story about question number nine," Moulton said. "As you
know, I am an advocate of S&OP, which is why I went to a seminar on strategy
and vision as preparation for giving this presentation. The presenter asked the
room, 'How many of you have heard of S&OP?' Amazingly, only 50% of the
participants raised their hands. Then the presenter asked, 'How many of you have a defi ned S&OP process?' Guess how many people raised their hands then? Just one! These were sophisticated companies in attendance, too."
10.) Do you have a visible leader of your supply chain?
"This question was one of many from an article I read," Moulton said. "It
asked a number of best questions. Its basic proposition was this: if you can't
answer these questions as 'yes,' then you probably are the problem. I suggest
you all read it."
11.) Is there visible support from the executive level?
"How would you know whether the support was visible?" Mulcahy asked.
"You would ask the question more specifi cally," Moulton said. "'Do my CFO
and CEO have visible knowledge and interest in the outcome of that meeting?'
This spawns further questions, such as…"
12.) How well does the meeting reflect reality?
13.) Can you use the meeting to adjust to either market or
operational situations?
14.) Are the results understood and incorporated into the
perfect plant?
"One way to know that the results are not being used productively," Moulton
said, "is to ask the manager if he is continuously juggling calls from multiple
sales people, production management, and senior management asking whether
they need to change grades or insert a given order. If so, there are people who don't understand what the manager is being measured against. There isn't a clear distinction of roles."
15.) How many of your maintenance decisions are made
with good data, tested data, or quality information,
and in how many of them do you let the economics
do the talking?
"I think we all know the most likely response to this question," Moulton said.
Perfect Plant Playbook
"To close this afternoon," Moulton said, "I'll take you through some quick
pointers on how to get started with optimizing strategy, planning, and
coordination at the perfect plant. You can make a real dent in a strategically
challenged organization armed with little more than a pencil and spiral
notebook.
"Let's start with simple supply-demand balancing. It's amazing how much it
can enhance your overall understanding of how to improve things. It just gets
people thinking in a more collaborative manner and forces the issue.
"And before you worry too much about software, it's critical to account for
your plant's S&OP. If nobody seems to know what it is, then either you don't
need it, because operations are so simple, or you need it badly. If your planners
are creating 90-day targets but you only get a feedback loop from the plant
once a month, you need an intermediary enforcer, or group of enforcers and
mediators, to ensure that the information fl ows between the two camps.
Without the intermediary, valuable information is just leaking away.
"Suppose you do want to create a responsive, tactical planning system with
real-time updates to the process representations in the model. It may involve
the scary but necessary step of ditching your current planning tool. A
familiar system that's inadequate now will only limit the performance of the
integrated system.
"You also need to examine the structure of your process. Before installing
any software, you may need to reorganize your people. In fact, if you don't
do this first, the stage may be set for a big software failure. Many plants
are run from the top-down, where the plan is imposed on schedule and
processes. If processes deviate from the plan, the process supervisors or
plant managers have to explain why. This results in poorly defined targets
for advanced process control systems when it comes time to automate. If you
look at strategy from a bottom-up approach, where the plan is tuned to the
process, the processes are still subject to targets and specifications. But you
can update and re-run the plan as many times as necessary to balance it with
the processes. Once you figure out if that works, then you can think about
the software you need.
"I'll leave you with 11 critical success factors," Moulton said, and wrote more
on the board, "that I cribbed from a lovely book called Planning, Scheduling and
Control Integration in the Process Industries, by C. Edward Bodington.
"In order to implement a successful integration of planning, scheduling, and
control, you need…"
The Critical Success Factors
- A realistic and well-documented business process model and material
flow diagram of what you want and expect to achieve, the timing,
and the activities and ownership identified.
- A Process Information System for real time data collection and
analysis of process operations that is blueprinted and configured to
support the expected business process model.
- Data communications networks for easy, standardized transfer of
information between elements.
- A central, rationalized database for storage and dissemination of all
input and results.
- Model-based data reconciliation both for the overall plant, and for
the individual processes.
- Advanced Process Control, including process optimization.
- A formal computerized scheduling system to manage process
interactions and inventories, to capture and report production and
shipments against plan into a form useful to the advanced process
control systems.
- A responsive tactical planning system with real time updates to the
process representations. A plan redeveloped as often as necessary
to maintain coordination between customer requirements and the
processes.
- Expert System applications imbedded in all the other elements to
interpret data and results and improve the efficiency of data
analysis.
- Process models tuned in real time so that planning predictions for
current operation agree with actual performance.
- An organizational structure that rewards cooperation and teamwork.
"While this advice was gained from experience in the process industries, it's
not hard to generalize these lessons," said Moulton.
"It is clear these points come from experience," said Mulcahy. "This was a
fascinating session, Peter. Thanks for your effort."