ERP: Making It Happen: The Implementers' Guide to Success with Enterprise Resource Planning
Chapter 5, Getting Ready
In this excerpt, find an introduction to ERP and learn what questions you should ask before deciding on implementation. Discover how to build a business case for ERP and who should be educated before implementation begins.

ERP: Making It Happen: The Implementers' Guide to Success with Enterprise Resource Planning, Ch. 5
Table of contents:
Preparing an ERP implementation plan: ERP audit and assessment
Introduction to ERP and designing a business case for ERP
ERP cost benefit analysis for stand-alone projects
FIRST-CUT EDUCATION
Key people need to learn about ERP before they can do a proper job
of creating the vision statement and estimating costs and benefits.
They need to learn five crucial elements:
1. What is ERP?
2. Is it for us? Does it make sense for our business?
3. What will it cost?
4. What will it save? What are the benefits we'll get if we do it the
right way and get to Class A?
and finally, if the company does not have Enterprise Software, but
needs/wants it,
5. What are the linkages with ES and should we do both at the
same time?
Some individuals may go through first-cut education prior to audit/
assessment. Either they will not be aware of the value of the audit/
assessment step or may want to become familiar with ERP prior
to audit/assessment. The sequence is not important; the critical issue
is to make sure that both steps are done. A management team should
make a decision to proceed with ERP (or any other major initiative,
for that matter) only after doing both audit/assessment I and first-cut
education.
Some companies attempt to cost justify ERP before they understand
what it's all about. Almost invariably, they'll underestimate the
costs involved in implementation. They'll feel ERP is part of the
computer system to order material. Therefore, most of the costs will
be computer related and already funded with ES or other software
projects. As a result, the project will not be properly funded.
Further, these companies almost always underestimate the benefits.
If they think ERP is a computer system to order material, then
most of the benefits will come from inventory reduction. It then becomes
very difficult to peg the ERP implementation as a high priority
in the company. The obvious moral of the story: First, learn about
it; then do the cost/benefit analysis.
Who needs first-cut education? For a typical company, these
people would be:
The CEO or general manager and the vice presidents of engineering,
finance, manufacturing, and the marketing/sales departments. Basically,
this should be the leadership team of the company or business
unit.
Managers from the sales department, customer service, logistics,
production, information systems, engineering, accounting, materials,
and supply chain management. Sales manager, customer service
manager, production manager, logistics manager, systems manager,
production control manager, purchasing manager, engineering manager,
accounting manager. Obviously, the composition of this group
can vary greatly from company to company. In smaller companies,
top management and operating management are often one and the
same. Larger companies may have senior vice presidents, directors,
and others who would need early education on ERP. The guidelines
to follow are:
1. Don't send many more people through first-cut education
than necessary, since the final decision to implement hasn't yet
been made.
2. On the other hand, be certain to include all key people -- informal
leaders as well as formal -- who'll be held accountable
for both costs and benefits. Their goal is to make an informed
decision.
Sometimes companies have a difficult time convincing certain senior
managers, possibly the general manager, to go through a first-cut education
process. This can be a very serious problem, and Chapter 7
will address it in detail.
VISION STATEMENT
In this step, the executives and operating managers who participated
in first-cut education develop a written vision of the company's transformation:
what will we look like and what new competitive capabilities
will be in place following the implementation of ERP (and perhaps
the ES/ERP combination). The statement must be written in a way
that can be measured easily, so it'll be obvious when you get there.
This step is easy to skip. It's easy to feel that it takes more time and
effort than it's worth. Not true. The reverse is actually the case: It's
not much work, and it's worth its weight in gold. It's an essential part of laying the foundation for a successful project, along with the
cost/benefit step. In fact, without a clear vision of the future, no sane
person would embark on the journey to work through the major
changes required.
The vision statement serves as a framework for consistent decision
making over the life of the project, and can serve as a rallying
point for the entire company. More immediately, the vision statement
will serve as direct input to downstream steps on the Proven
Path: cost/benefit analysis; establishment of performance goals; and
development of the demand management, planning, and scheduling
processes. Input to the preparation of the vision statement includes:
1. The executives' and managers' knowledge of:
- The company and its problems. (Where are we today?)
- Its strategic direction. (Where are we going?)
- Its operating environment. (What does the marketplace
require?)
- Its competition. (What level of performance would gain us
a competitive advantage in that marketplace?)
2. The recommendations made in audit/assessment I.
3. What was learned in first-cut education.
Brevity is good; less is more. Ideally, the vision statement will consist
of one page. Some great vision statements are little more than one
paragraph. It should be visceral, and it should drive action.
Since it's a relatively brief document, it shouldn't take a long time
to prepare. One or several meetings should do the job, with heavy involvement
by the general manager. However, if the vision is not clear
and accepted by the leadership, or if it is not aligned with the company's
strategy, don't go further. Remember, if the team doesn't know
where they are going, everyone will work hard in different, and often
conflicting directions.
One last point: Don't release the ERP vision statement quite yet.
Remember, you haven't yet made a formal go/no-go decision. That'll
come a bit later.
COST/BENEFIT ANALYSIS
Establishing the costs and benefits of an ERP project is essential.
Here are some reasons why:
1. High priority.
Job 1 is to run the business. Very close to that in importance should
be implementing ERP. It's very difficult to keep ERP pegged as a
very high priority if the relevant costs and benefits have not been established
and bought into. If ERP doesn't carry this high priority, the
chances for success decrease.
2. A solid commitment.
Implementing ERP and ES means changing the way the business is
run. Consequently, top management and operating management
must be committed to making it happen. Without a solid projection
of costs and benefits, the necessary degree of dedication may not be
attained, and the chances for success will decrease sharply.
3. One allocation of funds.
By identifying costs thoroughly and completely before implementation,
the company has to process only one spending authorization.
This avoids repeated "trips to the well" (the board of directors, the
corporate office, the executive committee) and their attendant delays
during the life of the project. This factor leads some companies to
combine ERP and ES into one project.
The people who attended first-cut education should now develop
the cost/benefit study. Their objective is to develop a set of numbers
to use in deciding for or against ERP. Do not, under any circumstances,
allow yourselves to skip this step. Even though you may be
convinced that you must do ERP and its benefits will be enormous,
it's essential that you go through this process, for the reasons mentioned
above. To do otherwise is like attempting to build a house on
a foundation of sand.
Let's first focus on the likely areas of costs and benefits. After that,
we'll work through several sample cost/benefit analyses.
Costs
A good way to group the costs is via our ABC categories: A = People,
B = Data, C = Computer. Let's take them in reverse order.
C = Computer.
Include in this category the following costs:
1. New computer hardware necessary specifically for ERP or ES.
2. ES software for a combined ERP/ES project, and possibly
supply chain bolt-ons for either ERP/ES or ERP only.
3. Systems people and others to:
- Configure and enhance the ES software.
- Install the software, test it, and debug it.
- Interface the purchased software with existing systems that
will remain in place after ERP and ES are implemented.
- Assist in user training.
- Develop documentation.
- Provide system maintenance.
These people may already be on staff, may have to be hired, and/or
may be temporary contract personnel. Please note: These costs can
be very large. Software industry sources report cost ratios of up to
1:8 or more. In other words, for every dollar that a company spends
on the purchased software, it may spend eight dollars for these installation
activities.
4. Forms, supplies, miscellaneous.
5. Software maintenance costs. Be sure to include the any expected
upgrades of the new software here.
6. Other anticipated charges from the software supplier (plus
perhaps some contingency money for unanticipated charges).
B = Data.
Include here the costs involved to get and maintain the necessary
data:
1. Inventory record accuracy, which could involve:
- New fences, gates, scales, shelves, bins, lift trucks, and
other types of new equipment.
- Mobile scanners on lift trucks to read bar codes on stock.
- Costs associated with plant re-design, sometimes necessary
to create and/or consolidate stockrooms.
- Cycle counting costs.
- Other increases in staffing necessary to achieve and maintain
inventory accuracy.
2. Bill of material accuracy, structure, and completeness.
3. Routing accuracy.
4. Other elements of data such as forecasts, customer orders,
item data, work center data, and so forth.
A = People.
Include here costs for:
1. The project team, typically full-time project leader and also
the many other people identified with individual segments of
the business.
2. Education, including travel and lodging.
3. Professional guidance.
4. Increases in the indirect payroll, either temporary or ongoing,
not included elsewhere. Examples include a new demand
manager or master scheduler, additional material planning
people, or another dispatcher. For most companies, this number
is not large at all. For a few, usually with no planning function
prior to ERP, it might be much higher.
These are the major categories of cost. Which of them can be eliminated?
None; they're all essential. Which one is most important? The
A item, of course, because it involves the people. If, for whatever reason,
it's absolutely necessary to shave some money out of the project
budget, from where should it come? Certainly not the A item. How
about cutting back on the C item, the computer? Well, if you absolutely
have to cut somewhere, that's the best place to do it. But why
on earth would we say to cut out computer costs with the strong ES
linkage with ERP?
The answer goes back to Chapter 1-- installing ES without the
proper ERP demand management, planning and scheduling tools
will gain little. Many companies have had decent success without
major computer or information system changes by working hard on
their ERP capability. Obviously, we recommend that you do both.
But, if there is a serious shortage of resources, do the planning systems
first and automate the information systems later. Later in this
chapter, we'll show you an example of the costs of the full ERP/ES
combination and also ERP alone.
Companies are reporting costs for the total ERP/ES installation
over $500 million for a large multinational corporation. In our
ERP/ES example, the company is an average-sized business unit
with $500 million in sales and about 1000 people, and the projected
costs are over $8 million to do the full job. This number is not based
on conjecture but rather on the direct experience of many companies.
Our sample company doing ERP alone (no ES, a much less intensive
software effort) shows considerably lower costs, but still
a big swallow at $3.9 million. These are big numbers; it's a big
project.
Benefits
Now let's look at the good news, the benefits.
1. Increased sales, as a direct result of improved customer service.
For some companies, the goal may be to retain sales lost to aggressive
competition. In any case, the improved reliability of the total
system means that sales are no longer lost due to internal clumsiness.
ERP has enabled many companies to:
- Ship on time virtually all the time.
- Ship in less time than the competition.
- Have their sales force spend their time selling, rather than
expediting shipments and making excuses to customers
over missed shipments.
In short, ERP can represent a significant competitive weapon. Surveys
of ERP-using companiesi have verified improved customer service
gains of 15 percent for all respondents; 26 percent for the
companies who identified themselves as Class A. For most companies,
better customer service means more sales.
2. Increased direct labor productivity, resulting from the valid, attainable
schedules which ERP can enable companies to have. Productivity
is increased via:
- Providing matched sets of components to the assembly areas,
thereby eliminating much of the inefficiency and idle
time often present.
- Reducing sharply the amount of expediting, lot splitting,
emergency changeovers, short runs, and so forth in the fabrication
areas.
- Requiring much less unplanned overtime, because the forward
visibility is so much better.
Survey results show respondents reporting an average productivity
gain of 11 percent; the Class A users got 20 percent. Think of the
value to the bottom line of that kind of productivity gain!
3. Reduced purchase cost. ERP provides the tools to give suppliers
valid schedules and better forward visibility. Once the customer
company gets out of the order-launch-and-expedite mode, its suppliers
can produce the customer's items more efficiently, at lower
cost. A portion of these savings can be passed back to the buying
company to be used either for increased profits or reduced product
pricing which can mean increased sales and profits.
Further, valid schedules can free the buyers from a life of expediting
and paper shuffling, so that they can do the important parts of
their jobs (sourcing, negotiation, contracting, value analysis, cost reduction, etc.). Therefore, these savings don't come solely from lower
prices but rather from reducing total purchase costs. Survey results:
Companies report an average reduction in total purchased costs of 7
percent; the Class A companies got 13 percent. In many companies,
the single largest financial benefit from ERP comes from purchase
cost reduction.
4. Reduced inventories. Effective demand management, planning,
and scheduling result in valid schedules.Valid schedules mean
matched sets of components, which means making the products on
schedule and shipping them on time. This typically results in lower
inventories at all, or at least most, levels—raw material, work-inprocess,
finished goods.
For most companies, the four benefit areas identified above are the
big ones. However, there are other benefits that are potentially very
significant and should not be overlooked. They include:
5. Reduced obsolescence, from an enhanced ability to manage engineering
changes, better forward visibility, and an overall smaller risk
of obsolescence due to lower inventories in general. This is often a hidden
cost at most companies and no one likes to focus on the stuff that
is sold at discount or thrown away. However, it can be very large and
certainly requires attention.
6. Reduced quality costs. Valid schedules can result in a more
stable environment, which can mean less scrap. Eliminating the endof-
the month lump, where perhaps 75 percent of the shipments go
out in the last 25 percent of the month, can lead to reduced warranty
costs.
7. Reduced premium freight, both inbound, by having a better
handle on what's needed, and outbound, by being able to ship on
time. Many companies are delighted when they can air express a
shipment to fulfill a customer order without thinking about the
money that they could have saved with an on-time land shipment.
8. Elimination of the annual physical inventory. If the inventory
numbers are accurate enough for ERP, they'll be more than good
enough for the balance sheet. Many Class A and B companies don't
take annual physical inventories. This can be a substantial savings in some companies. It can include not only the costs of taking the inventory
itself but also the costs of disrupting production, since many
companies can't produce while they count.
9. Reduced floor space. As raw material, work-in-process, and finished
inventories drop sharply, space is freed up. As a result, you may
not need to expand the plant or build the new warehouse or rent more
office space for some time to come. Do a mental connection between
ERP and your building plans. You may not need as much -- or any -- new brick and mortar once you get really good at manufacturing.
Don't build a white elephant.
10. Improved cash flow. Lower inventories mean quicker conversion
of purchased material and labor costs into cash.
11. Increased productivity of the indirect workforce. ERP will help
not only the direct production associates to be more productive but
also the indirect folks. An obvious example is the large expediting
group maintained by some companies. Under ERP, this group
should no longer be needed, and its members could be absorbed into
other, more productive jobs.
Another aspect of this, more subtle and perhaps difficult to quantify,
is the increased productivity of the supervisors and managers.
That includes engineers, quality control people, production supervisors
and managers, vice presidents of marketing, and let's not forget
about the guy or gal in the corner office -- the general manager. They
should all be able to do their jobs better when the company is operating
with a valid game plan and an effective set of tools to help them
execute it.
They'll have more fun, also. More satisfaction from a job well
done. More of a feeling of accomplishment. That's called quality of
life and, while it's almost impossible to quantify that benefit, it may
be the most important one of all.
Responsibility
A question often asked is: "Who should do the cost/benefit analysis?
Who should put the numbers together?" First of all, it should not be
a one-person process -- it's much too important for that. Second, the
process should not be confined to a single group. Let's look at several
ways to do a cost/benefit analysis:
Method 1: Middle management sells up.
Operating managers put together the cost/benefit analysis and then
attempt to sell the project to their bosses. If top management has been
to first-cut education, there should be no need for them to be sold.
Rather, they and their key managers should be evaluating specifically
how ERP will benefit their company and what it'll cost to get to Class A.
This method is not recommended.
Method 2: Top management decree.
The executive group does the cost/benefit analysis and then decrees
that the company will implement ERP. This doesn't allow for
building the kind of consensus and teamwork that's so important.
This method is not recommended.
Method 3: Joint venture.
This is the recommended approach. The cost/benefit analysis
should be done by those executives and managers who'll be held accountable
for achieving the projected benefits within the framework
of the identified costs. Here's how to do it:
1. A given department head, let's say the manager of sales administration
and customer service, attends first-cut education.
2. The vice president of the sales and marketing department attends
first-cut education.
3. Upon returning to the company, both persons do some homework,
focusing on what benefits the sales side of the business
would get from a Class A ERP system, plus what costs might
be involved.
4. In one or several sessions, they develop their numbers. In this
example, the most likely benefit would be increased sales resulting
from improved customer service, and the biggest cost
elements might be in education and training.
5. This process is also done in the other key functional areas of the
business. Then the numbers are consolidated into a single statement of costs and benefits in all of the key areas of the business
(finance, manufacturing, logistics, product development, etc.).
Please note the participatory nature of the joint venture approach.
Since both top management and operating management are involved,
it promotes consensus up and down the organization, as well
as cross functionally. We've found it to be far better than the other
approaches identified above.
A word of caution: Be fiscally conservative. When in doubt, estimate
the costs to the high side and the benefits low. If you're not sure
whether certain costs may be necessary in a given area, include them.
Tag them as contingency if you like, but get 'em in there. There's little
risk that this approach will make your cost/benefit numbers unattractive
because ERP is such a high payback project. Therefore, be
conservative. Don't promise more than you can deliver.
We'll give you an example of the costs and benefits to illustrate the
potential. You know that your company will have different numbers,
but we want to show that a conservative approach still gives big savings.
Note that the dramatic savings that are shown are still VERY
conservative.
Examples of Cost/Benefit Analysis
To illustrate the process, let's create a hypothetical company with the
following characteristics:
Annual sales: $500 million
Employees: 1000
Number of plants: 2
Distribution centers: 3
Manufacturing process: Fabrication and assembly
Product: A complex assembled make-to-order product, with many
options
Pretax net profit: 10 percent of sales
Annual direct labor cost: $25 million
Annual purchase volume (production materials): $150 million
Annual cost of goods sold: $300 million
Current inventories: $50 million
Combined ERP/ES
Let's take a look at its projected costs and benefits both for a combined
ERP/ES implementation and then for an ERP only project.
First, a warning:
Beware! The numbers that follow are not your company's numbers.
They are sample numbers only. Do not use them. They may be too
high or too low for your specific situation. Using them could be hazardous
to the health of your company and your career.
With that caution, let's examine the numbers. Figure 5-2 contains
our estimates for the sample company. Costs are divided into onetime
(acquisition) costs and recurring (annual operating) costs . . .
and are in our three categories: C = Computer, B = Data, A = People.
Note that we have not tried to adjust the payout period or the rate of
return for the obvious tax consequences of expenses versus capital.
This is for simplicity (but also recognizes that the great majority of the
costs are current expenses, and that expenses considered as capital investment
represent a relatively small number). You may want to make
the more accurate, tax-sensitive calculation for your operation.
These numbers are interesting, for several reasons. First, they indicate
the total ERP/ES project will pay for itself in seven to eight
months after full implementation.
Second, the lost opportunity cost of a one-month delay is
$1,049,250. This very powerful number should be made highly visible
during the entire project, for several reasons:
1. It imparts a sense of urgency. ("We really do need to get ERP
and ES implemented as soon as we can.")
2. It helps to establish priorities. ("This project really is the number
two priority in the company.")
3. It brings the resource allocation issue into clearer focus.
Regarding this last point, think back to the concept of the three
knobs from Chapter 2 -- work to be done, time available in which to do it, and resources that can be applied. Recall that any two of these
elements can be held constant by varying the third.
Too often in the past, companies have assumed their only option
is to increase the time. They assumed (often incorrectly) that both
the work load and resources are fixed. The result of this assumption:
A stretched-out implementation, with its attendant decrease in the
odds for success.
Making everyone aware of the cost of a one-month delay can help
companies avoid that trap. But the key people really must believe the
numbers. For example, let's assume the company's in a bind on the
project schedule. They're short of people in a key function. The
choices are:
1. Delay the implementation for three months. Cost: $3,147,750
($1,049K x 3).
2. Stay on schedule by getting temporary help from outside the
company (to free up the company's people to work on ERP and
ES, not to work on these projects themselves). Cost: $300,000.
Few will deny $300,000 is a lot of money. But, it's a whole lot less than
$3,147,750. Yes, we know this is obvious, but you would be amazed
at how many companies forget the real cost of delayed benefits.
So far in this example, we've been talking about costs (expenses) and
benefits (income). Cash flow is another important financial consideration,
and there's good news and bad news here. First, the bad news.
A company must spend virtually all of the $8 million (one-time
costs) before getting anything back. The good news: Enormous
amounts of cash are freed up, largely as a result of the inventory decrease.
The cost/benefit analysis for the total effort projects an inventory reduction of $10 million (10 percent of $25 million raw material
and work in progress and 30 percent of $25 million in finished
product). This represents incoming cash flow. (See Figure 5-3 for details.)
The company does have negative cash flow in year 1 since most
costs occur (as with virtually every project) before savings materialize.
However, while the cumulative cash position is still negative at
the end of year 2, the project will have generated over $5 million of
cash for that year. By year 3, you are generating cash in a big way.
How many large projects has your company undertaken that have
no cash impact in the second year with full savings in the third? We
bet not many. For our example company, ERP and ES appear to be
very attractive: An excellent return on investment (193 percent) and
substantial amounts of cash delivered to the bank.
Figure 5-2 Sample Cost/Benefit Analysis: Full ERP/ES
| COSTS |
| Item | One Time | Recurring | Comments |
| C - Computer |
| Hardware | $400,000 | | Costs primarily for workstations. |
| Software | 500,000 | $75,000 | Can vary widely, based on package. |
| Systems and programming | 2,500,000 | 200,000 | Adapting the software to your company, and training in its use. These costs are pegged here at 5 times the software purchase cost. |
| B - Data |
| Inventory record accuracy | 700,000 | 100,000 | Includes new equipment and added cycle counters. |
| Bill of material accuracy and structure | 200,000 | | Bills will need to be restructured into the modular format. Experienced engineers will be needed for this step. |
| Routing accuracy | 100,000 | | |
| Forecasting | 200,000 | 100,000 | Full time person for Sales forecasting. Needs to come on board early. |
| A - People |
| Project Team | 1,200,000 | | Six full-time equivalent people for two years. |
| Education | 800,000 | 100,000 | Includes costs for education time and teaching the new ES interactions to the organization. |
| Professional guidance | 400,000 | 50,000 | 4 days per month during installation. |
| SUB-TOTAL | $7,000,000 | $725,000 | |
| Contingency | $8,050,000 | $834,000 | |
| 15% | 1,050,000 | 109,000 | A conservative precaution against surprises. |
| TOTAL | $9,100,000 | $943,000 | |
| BENEFITS |
| Item | Current | % Improvement | Annual Benefits | Comments |
| Sales | $500,000,000 | 7% at 10% | $3,500,000 | Modest improvement due to improved product availability at the profit margin of 10%. |
| Direct labor productivity | 25,000,000 | 10% | 2,500,000 | Reductions in idle time, overtime, layoffs, and other items caused by the lack of planning and information flow. |
| Purchase cost | 150,000,000 | 5% | 7,500,000 | Better planning and information will reduce total purchase costs. |
| Inventories | | | | One time cash flow: |
| Raw Material and WIP | 25,000,000 | 10% at 15% | 380,000 | 2,500,000 |
| Finished goods | 25,000,000 | 30% at 15% | 1,130,000 | 7,500,000 |
| Obsolescence | 500,000 | 30% | 150,000 |
| Premium freight | 1,000,000 | 50% | 500,000 | Produce and ship on time reduces emergencies. |
| SUB-TOTAL | | | $15,660,000 | $10,000,000 One time cash flow. |
| Less costs for: |
| Contingency | | 15% | -2,349,000 | 1,500,000 |
| Recurring | | | -720,000 |
| NET ANNUAL BENEFITS | | | $12,591,000 | $8,500,000 One time cash flow. |
| Cost of a one month delay (Total/12) | $1,049,250 |
| Payback time (One Time Cost/monthly benefits) | 7.7 months |
| Return on investment (Annual benefits/One Time Costs) | 193% |
Figure 5-3 Projected Cash Flow from ERP/ES
| Year | Annual | Cumulative | Comments |
| 1 | -$6,440,000 | -$6,440,000 | 80% of remaining costs |
| 2 | -1,610,000 | | Remainder (20%) of one-time cost |
| -417,000 | | 6 months of recurring cost |
| +5,036,400 | | 40% of annual benefit |
| +2,125,000 | | 25% of inventory reduction |
| +5134,000 | -$1,306,000 |
| 3 | -834,000 | | Annual recurring cost |
| +12,591,000 | | Gross annual benefits |
| +6,475,000 |
| +18,233,000 | +$16,926,000 | Balance 75% of inventory reduction |
| | | Total cash flow at end of year 3 |